Summer 2001: No Summer Vacation. Work continued throughout the season, with construction workers starting at 7 a.m. and finishing at 10 p.m. (One reason the rebuilding is advancing at such a fast pace.)
Fall 2001: Rebuilding of the main dome starts.
Fall/Winter 2001: Interior rebuilding starts.
March 2002: Exterior Construction completed; dismantling of scaffolding. (By that time, the Frauenkirche will be visible above the scaffolding.)
End of 2003: Completion of 205- foot dome projected.
|

Construction workers at the Frauenkirche
Hand Blown Glass for the Frauenkirche’s Windows
In the spirit of the reconstruction, the Frauenkirche’s 36 feet high windows are now being installed in the same way the originals were. The artisans are installing fine, hand blown panes of antique-style glass between the sandstone mullions.
One concession to 21th century technology: High quality insulating glass will be installed on the interior side, which will provide weather and noise insulation.
The windows should be completed by the end of the year, allowing the interior work to proceed, protected from the winter weather.
|